Pre-Cast Pilling Works:
Ashraf Trade International have started the Pre-cast pilling business in 2011. We have 25 (twenty five) members technician team who run the pile equipments. We have completed Pre-Cast pilling work in many places in Bangladesh and provided the service for many clients. Some important clients are mentioned below.
PRAN-RFL Group
Site consist of 1000 piles
Completed
2014-2015
Re-Powering Project of Bangladesh Ghorashal 3rd unit 420MW Gas Based Combined Cycle Power Plant Under [China Energy Engineering Group Northeast No. 1 Electric Power Construction Co., (NEPC) ]
Site Consist of 800 Piles
Completed
2015-2016
Ghorashal Municipality, Palash, Narsingdi.
Completed 2000 piles in Municipal area.
Work Completed Certificate shown in our gallary box.